From: Brightwave Ltd (integration vendor) Re: Customer Portal - integration status Sent: 2026-05-18 Hello, A quick status update on our side of the portal integration. The payment gateway integration is going well. However, end-to-end integration testing cannot begin until 2 June, and we expect it to take a further five working days to complete. That puts our realistic readiness date at 9 June 2026. We understand a date has been communicated externally, but we would strongly advise against switching off the legacy system until integration testing has passed. Running both systems in parallel for a short window would be much safer. We can provide a dedicated engineer for the cutover weekend if helpful. Regards, Brightwave Integration Team